Critical Success Factors for Malaysian Construction Projects: An Investigative Review

Authors

  • Yee Cheong Yong Department of Quantity Surveying, Faculty of Built Environment, Universiti Teknologi Malaysia.
  • Nur Emma Mustaffa Department of Quantity Surveying, Faculty of Built Environment, Universiti Teknologi Malaysia.

DOI:

https://doi.org/10.11113/ijbes.v4.n2.180

Abstract

Construction projects play an important role in the advancement of a nation through infrastructure development that leads to economic growth. They are planned carefully to accomplish certain goals. However, not all the projects achieved the goals as per planned. Many factors contribute to the successes and failures, and it becomes an interesting arena for research. The primary objective of this paper is to outline the development trend of project success measurement globally and locally. The research method employed was to make selected reviews on critical success factors' (CSFs) literature and to compare international standards and progress in incorporating human behavioural aspects of project management to the situation in Malaysia. A somewhat similar pattern can be observed in Malaysia where the studies have departed from the usual criteria of time, cost and quality, to define project success in a more holistic way. However, the domestic industry has failed to respond to the emerging trend globally as there has yet been any widely published research on the importance of human-related factors towards project success. A consolidated framework of CSFs has therefore, been proposed in responding to the findings. This paper fulfils an identified need as there has been a dearth of research on the subject matter locally.

References

Agarwal, S. (1994), "Socio-Cultural Distance and the Choice of Joint Ventures: A Contingency Perspective", Journal of International Marketing, Vol. 2 No. 2, pp. 63-80.

Akintoye, A., McIntosh, G. and Fitzgerald, E. (2000), "A survey of supply chain collaboration and management in the UK construction industry", European Journal of Purchasing and Supply Management, Vol. 6 No. 3, pp. 159-168.

Alaghbari, W., A. Kadir, M. R., Salim, A. and Ernawati (2007), "The significant factors causing delay of building construction projects in Malaysia", Engineering, Construction and Architectural Management, Vol. 14 No. 2, pp.192-206.

Al-Tmeemy, S. M. H. M., Abdul-Rahman, H. and Harun, Z. (2011), "Future criteria for success of building projects in Malaysia", International Journal of Project Management, Vol. 29 No. 3, pp. 337-348.

Andersen, E. S. and Jessen, S. A. (2000), "Project evaluation scheme: A tool for evaluating project status and predicting project results", Project Management Journal, Vol. 6 No. 1, pp. 61-69.

Andersen, E. S., Jessen, S. A., Birchall, D. and Money, A. H. (2006), "Exploring project success", Baltic Journal of Management, Vol. 1 No. 2, pp. 127-147.

Atkinson, R. (1999), "Project management: cost, time and quality, two best guesses and a phenomenon, its time to accept other success criteria", International Journal of Project Management, Vol. 17 No. 6, pp. 337-342.

Axelrod, R. (1984), The Evolution of cooperation, Basic Books, New York.

Barlow, J., Cohen, M., Jashapara, A. and Simpson, Y. (1997) Towards Positive Partnering, The Policy Press, Bristol, UK.

Belassi, W. and Tukel, O. I. (1996), "A new framework for determining critical success/failure factors in projects", International Journal of Project Management, Vol. 14 No. 3, pp. 141-151.

Belout, A. and Gauvreau, C. (2004), "Factors influencing the project success: the impact of human resource management", International Journal of Project Management, Vol. 22 No.1, pp. 1-11.

Chan, A. (2002), "Framework of Success Criteria for Design/Build Projects", J. Manage. Eng., Vol. 18 No. 3, pp. 120-128.

Chan, A. (2004), "Factors Affecting the Success of a Construction Project", J. Constr. Eng. Manage., Vol. 130 No. 1, p. 153-155

Chan, D. W. M. and Kumaraswamy, M. M. (1996), "An evaluation of construction time performance in the building industry", Building and Environment, Vol. 31 No. 6, pp. 569-578.

Cheung S.O., Ng S.T., Wong S.P. and Suen H. (2003), "Behavioural Aspects of Construction Partnering", International Journal of Project Management, Vol. 21 No. 5, pp. 333-343.

Chua, D.K.H., Kog, Y. C. and Loh, P. K. (1999), "Critical success factors for different project objectives", Journal of Construction Engineering and Management, Vol. 125 No. 3, pp. 142–150.

CIDB Malaysia (2004), President’s & CEO’s Roundtable Discussion, “The Way Forward Towards Global Competitiveness” – Malaysian Construction Industry Master Plan (MCIMP), Construction Industry Development Board Malaysia, Kuala Lumpur, Malaysia.

CIDB Malaysia (2006), Construction Industry Master Plan (2006-2015): Construction Industry Development Board (CIDB), Kuala Lumpur.

Cooke-Davies, T. (2002), "The “real” success factors on projects", International Journal of Project Management, Vol. 20 No. 3, pp. 185-190.

Dainty, A. R. J., Bryman, A., Price, A. D. F., Greasley, K., Soetanto, R. and King, N. (2005), "Project affinity: the role of emotional attachment in construction projects", Construction Management and Economics, Vol. 23 No. 3, pp. 241-244.

Department of Statistics Malaysia (2013), Economic Report 2012/2013, Kuala Lumpur, Malaysia.

Department of Statistics Malaysia (2011), Economic Report 2011/2012: Department of Statistics (DOS) and Ministry of Finance (MOF) Malaysia, Kuala Lumpur.

de Wit, A. (1988), "Measurement of project success", International Journal of Project Management, Vol. 6 No. 3, pp. 164-170.

Dissanayaka, S. M. and Kumaraswamy, M. M. (1999), "Evaluation of factors affecting time and cost performance in Hong Kong building projects", Engineering, Construction and Architectural Management, Vol. 6 No. 3, pp. 287–298.

Eriksson, P.E. (2006), "Procurement and governance management: development of a conceptual procurement model based on different types of control", International Review of Management Studies, Vol. 17 No.1, pp. 30–49.

Fellows, R. (2010), "New research paradigms in the built environment", Construction Innovation: Information, Process, Management, Vol. 10 No. 1, pp. 5-13.

Fortune, J. and White, D. (2006), "Framing of project critical success factors by a systems model", International Journal of Project Management, Vol. 24 No.1, pp.53-65.

Gidado, K. I. (1996), "Project Complexity: The Focal Point of Construction Planning", Construction Management and Economics, Vol. 14 No. 3, pp. 213-225.

Hartman, F.T. (2002), "The role of trust in project management", in Slevin, D.P., Cleland, D.I. and Pinto, J.K. (eds) The frontiers of project management research, Project Management Institute, Newtown Square, PA, pp. 225-235.

Hatush, Z. and Skitmore, M. (1997), "Evaluating contractor prequalification data: selection criteria and project success factors", Construction Management and Economics, Vol. 15 No. 2, pp. 129-147.

Kadefors, A. (2004), "Trust in project relationships—inside the black box", International Journal of Project Management, Vol. 22 No. 3, pp. 175-182.

Kong, A. T. and Gray, J. (2006), "Problems With Traditional Procurement in the Malaysian Construction Industry - a Survey", In Runeson, G. a. B., Rick, (Ed.), Australasian Universities Building Educators Association Annual Conference, University of Technology, Sydney. Australasian Universities Building Educators Association, Sydney, pp. 1-21.

Korczynski, M (1996), "The Low-Trust Route to Economic Development: Inter-Firm Relations in the UK Engineering Construction Industry in the 1980s and 1990s", Journal of Management Studies, Vol. 33 No. 6, pp. 787-808.

Kumaraswamy, M. M. and Chan, D. W. M. (1999), "Factors facilitating faster construction", Journal of Construction Procurement, Vol. 5 No. 2, pp. 88–98.

Kumaraswamy, M., Love, P., Dulaimi, M. and Rahman, M. (2004). "Integrating Procurement and Operational Innovations for Construction Industry Development", Engineering, Construction and Architectural Management, Vol. 11 No. 5, pp. 323-334.

Li, B., Akintoye, A., Edwards, P. J. and Hardcastle, C. (2005), "Critical success factors for PPP/PFI projects in the UK construction industry", Construction Management and Economics, Vol. 23 No. 5, pp. 459-471.

Lim, C.F. (2005), "The Malaysian construction industry: the present dilemmas of unpaid contractors", Master Builders Association of Malaysia (MBAM) Journal, 4th Quarter, pp. 80–82.

Lim, C. S. and Mohamed, M. Z. (1999), "Criteria of project success: an exploratory re-examination", International Journal of Project Management, Vol. 17 No. 4, pp. 243-248.

Low, S.P. and Chuan, Q. (2006), 'Environmental factors and work performance of project managers in construction industry', International Journal of Project Management, Vol. 24 No.1, pp. 24–37.

Masterman, J.W.E. (2002), An introduction to building procurement systems, E&FN Spon, London, UK.

Mayer, R. C., Davis, J. H. and Schoorman, F. D. (1995), "An integrative model of organizational trust", The Academy of Management Review, Vol. 20 No.3, pp. 709-734.

Meng, X. (2012), "The effect of relationship management on project performance in construction", International Journal of Project Management, Vol. 30 No.2, pp.188–198.

Munns, A. (1995), "Potential influence of trust on the successful completion of a project", International Journal of Project Management, Vol. 13 No. 1, pp. 19-24.

Munns, A.K. and Bjeirmi, B.F. (1996), "The role of project management in achieving project success", International Journal of Project Management, Vol. 14 No.2, pp. 81-87.

Naoum, S. (2003), "An overview into the concept of partnering", International journal of project management, Vol. 21 No. 1, pp. 71-76.

Narayanan, S. and Lai, Y.-W. (2005), "The Causes and Consequences of Immigrant Labour in the Construction Sector in Malaysia", International Migration, Vol. 43 No. 5, pp. 31–57.

Navarre, C. and Schaan, J. L. (1990), "Design of Project Management System from Top Management's Perspective", Project Management Journal, Vol. 21 No. 2, pp. 19-27.

Nguyen, L. D., Ogunlana, S., O. and Lan, D. T. X. (2004), "A study on project success factors in large construction projects in Vietnam", Engineering, Construction and Architectural Management, Vol. 11 No. 6, pp. 404-413.

Nicolini, D. (2002), "In search of "project chemistry"", Construction Management and Economics, Vol. 20 No. 2, pp. 167-177.

Parfitt, M. and Sanvido, V. (1993), "Checklist of Critical Success Factors for Building Projects", J. Manage. Eng., Vol. 9 No. 3, pp. 243-249.

Pietroforte, R. (1997), "Communication and governance in the building process", Construction Management and Economics, Vol. 15 No. 1, pp. 71–82.

Pinto, J.K. and Slevin, D.P. (1988), "Critical success factors across the project lifecycle", Project Management Journal, Vol. 19 No. 3, pp. 67-75.

Pinto, J. K., Slevin, D. P. and English, B. (2009), "Trust in projects: An empirical assessment of owner/contractor relationships", International Journal of Project Management, Vol. 27 No. 6, pp. 638-648.

Rockart, J. F. (1982), "The Changing Role of the Information Systems Executive: A Critical Success Factors Perspective", Sloan Management Review, Vol. 24 No. 1, pp. 3-13.

Rockart, J. F. and Bullen, C. V. (1981), "A Primer on Critical Success Factors", working paper no. 69, Center for Information Systems Research, Sloan School of Management, MIT.

Sambasivan, M. and Soon, Y. W. (2007), "Causes and effects of delays in Malaysian construction industry", International Journal of Project Management, Vol. 25 No. 5, pp. 517-526.

Sanvido, V., Grobler, F., Parfitt, K., Guvenis, M. and Coyle, M. (1992), "Critical Success Factors for Construction Projects", J. Constr. Eng. Manage., Vol. 118 No. 1, pp. 94-111.

Shenhar, A. J., Levy, O. and Dvir, D. (1997), "Mapping the dimensions of project success", Project Management Journal, Vol. 28 No. 2, pp. 5–13.

Songer, A. D. and Molenaar, K. R. (1997), "Project characteristics for successful public sector design-build", Journal of Construction Engineering and Management, Vol. 123 No.1, pp. 34–40.

Takim, R. and Adnan, H. (2008), "Analysis of Effectiveness Measures of Construction Project Success in Malaysia", Asian Social Science, Vol. 4 No. 7, pp. 74–91.

Takim, R., Akintoye, A. and Kelly, J. (2004), ''Analysis of measures of construction project success in Malaysia'', Proceedings of the 20th Annual ARCOM Conference in Heriot Watt University, 1-3 September, Association of Researchers in Construction Management, Vol. 2, pp. 1123-1133.

Tiong, R. (1992), "Critical Success Factors in Winning BOT Contracts", J. Constr. Eng. Manage., Vol. 118 No. 2, pp. 217-228

Toor, S.-u.-R. and Ogunlana, S. O. (2008), "Critical COMs of success in large-scale construction projects: Evidence from Thailand construction industry", International Journal of Project Management, Vol. 26 No. 4, pp. 420-430.

Toor, S.-u.-R. and Ogunlana, S. O. (2009), "Construction professionals' perception of critical success factors for large-scale construction projects", Construction Innovation: Information, Process, Management, Vol. 9 No. 2, pp. 149-167.

Walker, D.H.T. (1995), "An investigation into construction time performance", Construction Management and Economics, Vol.13 No. 3, pp. 263–274.

Walker, D. H. T. and Hampson, K. (2003), Procurement Strategies - A Relationship-based Approach, Blackwell Science Ltd, Oxford, UK.

Yong, Y. C. and Mustaffa, N. E. (2012), "Analysis of factors critical to construction project success in Malaysia", Engineering, Construction and Architectural Management, Vol. 19 No. 5, pp. 543 - 556.

Yong, Y. C. and Mustaffa, N. E. (2013), "Critical success factors for Malaysian construction project: an empirical assessment", Construction Management and Economics, Vol. 31 No. 9, pp. 959 - 978.

Downloads

Published

2017-05-15

How to Cite

Yong, Y. C., & Mustaffa, N. E. (2017). Critical Success Factors for Malaysian Construction Projects: An Investigative Review. International Journal of Built Environment and Sustainability, 4(2). https://doi.org/10.11113/ijbes.v4.n2.180