Variability of Cost and Time Delivery of Educational Buildings in Nigeria

Authors

  • Douglas Omoregie Aghimien Department of Quantity Surveying, School of Environmental Technology, Federal University of Technology, Akure, Ondo State, Nigeria
  • Oluwaseyi Alabi Awodele Department of Quantity Surveying, School of environmental Technology, Federal University of Technology, Akure, Ondo State, Nigeria

DOI:

https://doi.org/10.11113/ijbes.v4.n3.208

Abstract

Cost and time overrun in construction projects has become a reoccurring problem in construction industries around the world especially in developing countries. This situation is unhealthy for public educational buildings which are executed with limited government funds, and are in most cases time sensitive, as they need to cater for the influx of students into the institutions. This study therefore assessed the variability of cost and time delivery of educational buildings in Nigeria, using a study of selected educational buildings within the country. A pro forma was used to gather cost and time data on selected building projects, while structured questionnaire was used to harness information on the possible measures for reducing the variability from the construction participants that were involved in the delivery of these projects. Paired sample t-test, percentage, relative importance index, and Kruskal-Walis test were adopted for data analyses. The study reveals that there is a significant difference between the initial and final cost of delivering educational buildings, as an average of 4.87% deviation, with a sig. p-value of 0.000 was experienced on all assessed projects. For time delivery, there is also a significant difference between the initial estimated time and final time of construction as a whopping 130% averaged deviation with a sig. p-value of 0.000 was discovered. To remedy these problems, the study revealed that prompt payment for executed works, predicting market price fluctuation and inculcating it into the initial estimate, and owner’s involvement at the planning and design phase are some of the possible measures to be adopted.

References

Abu-Shaban, S. S. (2008). Factors Affecting the Performance of Construction Projects in the Gaza Strip (M.Sc thesis), The Islamic University of Gaza. Palestine.

Aghimien, D. O., & Oke, A. E.(2015).Application of Value Management to selected Construction Projects in Nigeria, Developing Country Studies, 5(17), 8 – 14

Akindoyin, A. (1988). The management of abandoned projects. Journal of the Nigerian Institute of Building. Maiden edition, 16-20

Al-Momani A. H., (2000). Examining service quality within constructionprocesses. Technovation, 20, 643-651

Ameh, O. J., Soyingbe, A. A., & Odusami, K. T. (2010). Significant factors causing cost overruns in telecommunication projects in Nigeria. Journal of Construction in Developing Countries, 15.

Amu, O. O. & Adesanya, D. A. (2011). Mathematical Expressions for Explaining Project Delays in South western Nigeria. Singapore Journal of Scientific Research, 1, 59-67.

Ashworth, A. (2000). Cost Studies of buildings, 2nd Edition, Longman Group Limited

Azhar, N., Farooqui, R. U. & Ahmed, S. M. (2008). Cost Overrun Factors in Construction Industry of Pakistan: in First International Conference on Construction in Developing Countries (ICCIDC–I) “Advancing and Integrating Construction Education, Research & Practice”: NED University of Engineering and Technology, Karachi, Pakistan.

Bubshait, A. A. & Almohawis, S. A. (1994). Evaluating the general conditions of a construction contract. International journal of Project Management, 12(3), 133-135

Chan, & Chan, (2004) Measuring the Success of Building Projects – improved project delivery Initiatives.

Cohen, J., (1988). Statistical power analysis for the behavioral sciences. Hillsdale, NJ: Erlbaum

Edukugho, E. (2013). Education sector stinks! Infrastructure bad, now worse. Retrieved from http://www.vanguardngr.com/2013/12/education-sector-stinks-infrastructure-bad-now-worse/

Endut, I. R. Akintoye, A. & Kelly, J. (2009). Cost and time overruns of projects in Malaysia. Available on: http://www.irbnet.de/daten/iconda/CIB10633.pdf

Eshofonie F. P. (2008). Factors affecting cost of construction in Nigeria. Unpublished M.Sc theses. University of Lagos Akoka, Lagos.

Ewa U. E., (2013). Root Causes of Project Abandonment in Tertiary Institutions in Nigeria International Business Research; 6(11), 149 – 159

Fadokun, J. B. (2009). University research capacity in Nigeria and the challenges of National development in a knowledge-based economy. National Institute for Educational Planning and Administration, Nigeria. Available on: umconference.um.edu.my/upload/43-1

Fisk, E. R. (1997). Construction Project Administration 5th edition. Prentice Hall, New Jersey.

Frimpong Y., Oluwoye, J. & Crawford, L. (2003). Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study. International Journal of Project Management, 21, 321–326

Gkritza, K., & Labi, S. (2008). Estimating Cost Discrepancies in Highway Contracts: Multistep Econometric Approach. Journal of Construction Engineering and Management, 134.

Hussin, J. M., Rahman, I. A., & Memon, A. H. (2013). The Way Forward in Sustainable Construction: Issues and Challenges. International Journal of Advances in Applied Sciences, 2(1), 15-24.

Kikwasi, G. J. (2012). Causes and effects of delays and disruptions in construction projects in Tanzania. Australasian Journal of Construction Economics and Building, Conference Series, 1 (2) 52-59

Kumaraswamy, M. M. & Chan, W. M. (1998). What contributes to construction delays. Journal of Construction Management & Economics, 17-29.

Le-Hoai, L., Lee, Y. D. & Lee, J. Y. (2008). Delay and Cost Overruns in Vietnam Large Construction Projects: A Comparison with Other Selected Countries. KSCE Journal of Civil Engineering, 12, 367-377.

Lim, C., S. & Mohamed, M., Z. (1999). Criteria of Project Success: an exploratory re-examination. International Journal of Project Management, 17(4), 243-248

Mbachu, J. I. C & Nkando, R. N. (2004). Reducing Building Construction Costs: The Views of Consultants and Contractors. RICS COBRA Research Conference, Leeds Metropolitant University, UK, 7-8 September

Memon, A. H., Rahman, I. A., Abdullah, M. R. & Azis, A. A. (2010). Factors affecting construction cost performance in project management projects: case of Mara large projects. Proceedings of post graduate seminar on engineering, technology and social science. Universiti Tun Hussein Onn Malaysia

Memon, A. H., Rahman, I. A., Abdullah, M. R. & Azis, A. A. (2012). The Cause Factors Of Large Project’s Cost Overrun: A Survey In The Southern Part Of Peninsular; International Journal Of Real Estate Studies, 7(2), 1 – 15

Moser, C. A., & Kalton, G. (1999). Survey Methods in Social Investigation, 2nd Edition. Gower Publishing Company Ltd, Aldershot

National Institute of Building Sciences (2013). Estimating Methods. Available on: www.nibs.org/%3Fpage%3Dconference

Odediran, S. J, Adeyinka, B. F, Opatunji, O. A & Morakinyo, K. O. (2012) Business Structure of Indigenous Firms in the Nigerian Construction Industry. International Journal of Business Research and Management, 3(5), 255-264

Odediran,S. J., Adeyinka, B. F. & Eghenure, F. O. (2008). A Study Of Factors Influencing Overruns of Construction Projects in Nigeria. Journal of Architecture, Planning & Construction Management, 2(2) pp 20-36

Odeyinka, H. A. & Yusif, A. (1997). The causes and effect of construction delays on completion cost of housing projects in Nigeria. Journal of Financial Management Property and Construction, 2(3), 31-44

Ogbu, C. P (2017). Survival practices of indigenous construction firms in Nigeria. International Journal of Construction Management, 1-14

Ogunsemi, D. R & Jagboro, G. O. (2006). Time-Cost Model for Building Projects in Nigeria Construction Management and Economics 24, 253–258

Ogunsemi, D. R. (2015). Value for Money in Construction Projects: The Quantity Surveyor’s Quest. 71st Inagural Lecture delivered by Prof. D. R. Ogunsemi at the 2500 Capacity Auditorium, Federal University of Technology, Akure, Ondo State.

Omoregie, A. & Radford, D. (2006). Infrastructure delays and cost escalation: Causes and effects in Nigeria; in proceeding of sixth international postgraduate research conference: Delft University of Technology and TNO, 79-93.

Onuoha, L. N. (2013). Financing Higher Education in Nigeria: The Role of Internally Generated Revenues and How University Managements Can Maximize the Sources. Canadian Social Science, 9 (1), 9-14.

Oyedele, D. (2013). UI receives biggest allocation of intervention fund. Retrieved from http://www.thisdaylive.com/articles/ui-receives-biggest-allocation-of-intervention- funds/158465/

Sanusi, S. L. (2010). Growth prospects for the Nigerian economy. Convocation lecture delivered at the Igbinedion University Eighth Convocation Ceremony; Okada, Edo State.

Sushil, S. & Verma, N. (2010). Questionnaire Validation Made Easy. European Journal of Scientific Research, 46 (2), 172 – 178

Tabachnick, B. G., & Fidell, L. S. (2001). Using multivariate statistics (4th edn). New York: Harper Collins

Wong, J., Toe, M. & Cheng, Y. K. (2010). Cultural determinants of stress in the construction industry. Proceedings of 2010 International Conference on Construction and Real Estate Management, 1–3 December, 2010, Brisbane, Queensland.

Zujo, V., Car-Pusic, D. & Brkan-Vejzovic, A. (2010). Contracted price overrun as contracted construction time overrun function, Technical Gazette, 17, 23-29

Downloads

Published

2017-09-10

How to Cite

Aghimien, D. O., & Awodele, O. A. (2017). Variability of Cost and Time Delivery of Educational Buildings in Nigeria. International Journal of Built Environment and Sustainability, 4(3). https://doi.org/10.11113/ijbes.v4.n3.208